The MAIN JOURNAL for POWER GRID SPECIALISTS in RUSSIA
36
YAKUTSKAYA SDPP-2: HEAT AND
LIGHT OF THE SEVERE NORTH
Yakutia is isolated from an in-
tegrated power grid of the Russian
Federation. Nowadays it includes
three energy areas: Western,
Central and Southern Yakutsk, and
also a zone of the decentralized
power supply which is attended by
JSC “Sakhaenergo”. 94% of power
consumption of nine areas of the
republic and 54% of heatconsump-
tion in of Yakutsk (Central energy
area) are provided by Yakutskaya
SDPP constructed still in the six-
ties of the last century. Despite
the modernization of Yakutskaya
SDPP which was carried out in the
eighties, six of eight gas-turbine
installations of station have already
more than twice reached the end of
its service life.
Inhabitants of Yakutia perfect-
ly remember the accident in De-
cember, 2002 when the capital
and a third part of the population
Construction of Yakutskaya SDPP-2 is an event for the region more than just of
a large-scale. Especially taking into account that the energy situation in Yakutsk
and the central part of the republic has developed in a very dif
fi
cult way today.
Residents of the capital of the republic know
fi
rsthand how it is to be left without
heat and light when the temperature outside the window is 50 degrees below zero.
New Energy
of the Far East
37
of the republic have been left
without electricity, heat and water
for two hours at a temperature of
40 degrees below zero. That time
Yakutskaya SDPP has been com-
pletely stopped because of the ac-
cident on the sixth power unit and
mistakes in the actions of tech-
nicians. In November, 2008 in the
Central energy area high alert be-
cause of breakage of the gas-tur-
bine GTU-45 installation has been
again introduced. Both times were
succeeded to avoid catastrophic
consequences, however the situa-
tion is still very serious these days:
despite planned repairs, the station
has reached the end of its service
life and the outdated equipment of
Yakutskaya SDPP will be pulled
out of service since the next year.
Big Plans
The city of Yakutsk develops
more than just dynamically today.
Those who came there three-four
years ago cannot recognize the
city any more today – its appea-
rance has changed a lot. The in-
ternational airport, a large number
of social objects – schools, kinder-
gartens, sports units have been
constructed, and the housing stock
has increased by a third over the
last 10 years. The government of
the republic has proposed ambi-
tious strategy for development till
2032, which includes appearance
of dozens of new enterprises and
tourist objects.
Moreover, at the Eastern Eco-
nomic Forum which took place in
September, 2015 in Vladivostok,
the Republic of Sakha (Yakutia)
submitted 19 projects at the total
cost of 262.5 billion rubles; plans in
the
fi
eld of mining, development of
high technologies and transport are
among them. Even according to
the most conservative calculations
till 2020 electric loading of the
Central energy area of Yakutia
will grow by 70%, and load of heat
networks networks will increase
by 30%.
It is obvious that without a re-
liable source of energy resources
it is simply impossible to realize
the conceived. Replacement of
was required – it was necessary to
understand whether the buildings
would be able to sustain weight
during the summer months when
permafrost soil melts.
New Yakutskaya SDPP-2 is
built on two isolated platforms: one
of them is located on the mountain
Chochur-Muran, and another – at
its bottom. On the main platform
the main building of power plant,
the building of electrotechnical
devices, service buildings are
constructed. On the secondary
platform the incorporated building
for a central heat point, water
treatment plants, pumping plant
utility and drinking water supply
system with water-storage tanks
have been constructed. Platforms
are connected one to each other
by a pipe rack process.
The station will be under
construction in two construction
stages. The
fi
rst construction stage
of Yakutskaya SDPP-2 includes
four gas-turbine installations with
waste-heat recovery units and
three peak water-heating boilers
with plantwide infrastructure. The
second construction stage contains
three gas-turbine installations with
waste-heat recovery units. Four
gas-turbine installations of the
fi
rst construction stage power
facility – LM 6000 produced by
General Electric with a capacity of
42.3 MW and waste-heat recovery
YAKUTSKAYA SDPP-2
•
Objectives:
•
creation of electrical capacity reserve,
•
replacement of operating Yakutskaya SDPP retired capacity
•
Electrical capacity:
193.5 MW
(1st construction stage)
•
Heat capacity:
469 Gcal/h
(1st construction stage)
•
Total electrical capacity
of two construction stages:
338.6 MW
•
Total heat capacity
of two construction stages:
569.8 Gcal/h
•
Fuel:
natural gas of Srednevilyuisk gas and condensate
fi
eld
•
Р
opulation of the
Republic of Sakha (Yakutia) :
1 million people
•
Р
opulation of Yakutsk:
300 thousand people
seriously outdated capacities of
the Central energy area of the re-
public, and also improvement of
an ecological situation by means
of the partially removal of ineffec-
tive and ecologically harmful boiler
house of Yakutsk is also the main
objective of Yakutskaya SDPP-2
which is building now.
Yakutsk
New Heart
The
fi
rst construction stage of
Yakutskaya SDPP-2 is the one of
four drafts of the PJSC “RusHydro”
investment program for new
power facilities construction in
the Far East, realized jointly with
“RAO Energy Systems of the East”
according to Decree of the Russian
Federation President.
Construction of a new highly
effective gas-turbine combined
heat and power plant in Yakutsk is
a really unique event. Over the last
50 years it is the
fi
rst large thermal
power facility built in the conditions
of permafrost. Yakutskaya SDPP-2
project has no analog at present
time. What worth only concrete
works which were conducted within
the temperature of 40 degrees
below zero! The project attracted
special attention due to the severe
Yakutsk climate. In particular, long-
lasting examination of test piles
Fa
c
t s
h
e
e
t
38
stallations, gas pipelines of inner
circuits of waste-heat recovery
units and peak water-heating boi-
lers within the main building, gas-
turbine installations air conduits
comes to the end. At the building
of electrotechnical devices instal-
lation of Gas Insulated Switchgear
(GIS) cells with capacity of 110 kV
is conducted, which is necessary
for electrical energy receiving, dis-
tribution and transmission through
air-lines from the station to the
power supply system. Hydraulic
tests of a pipe rack process have
been carried out, hydraulic tests
of tanks with diesel (emergency)
fuel have been started, equip-
ment at the building of gas boost-
ing station and at the incorporated
building on the secondary plat-
form has being installed.
For Safety
and Comfort
Construction of the new power
facility on the territory of Yakutia
has attracted the attention of
the federal government, public
authorities of the republic, and
its residents. Importance of the
project was emphasized by the
vice-speaker of State Assembly
(Il Tumen) Olga Balabkina: “The
units with a capacity of 42.9 Gcal/h
are already mounted at the main
building of the station.
Unlike the classical SDPP used
for the development of electric
power only, the new station will
produce also heat. It will allow to
reduce considerably the number
of boiler rooms (now there are
more than 100 ones), which
provide service for the capital of
the republic and doing harm to
environment. Improvement of
the ecological situation will be
promoted also by use of natural
gas as fuel. Moreover, the place
for construction has been chosen
taking into account a wind rose,
due to that the smoke will leave
the city aside, and the location on
a height far from the city districts is
also favorable for the city ecology.
At the moment implementa-
tion of the project is in its active
phase. The main buildings and in-
stallations have been constructed,
delivery of the basic facilities has
been carried out and the main part
of works on installation has been
ful
fi
lled. Now the closing stage in-
cludes
fi
tting-up of the four waste-
heat recovery units – station
basic facilities, hydraulic tests
have been carried out. Also at
the main building installation of
gas pipelines to gas-turbine in-
matter of Yakutskaya SDPP-2
construction has been in a spot-
light for a long time. After all, we,
the citizens, want to turn on the
lights and to watch TV coming
home late in the evening. We
want the city streets lamps and
traf
fi
c lights to be switched on,
we want to see gleaming neon
fi
res of advertising, and also we
wish that kindergartens, schools,
hospitals would be warm and
full of light. We want our city
to become more beautiful for
living in a comfortable, safe
and homelike place. In modern
conditions social responsibility
of business is necessary for
successful implementation of
such global project, because
construction of such scale
won’t make a momentary pro
fi
t.
Members of business community
say that it is “long money”. And
there we are glad to see the
understanding attitude of the
RusHydro company, where the
safety of the republic residents is
an understandable matter and not
just a
fl
uent phrase. Protection of
the population from technogenic
incidents, creation of conditions
when life will be safe and
comfortable, all these become the
main motto of current construc-
tions”.
Yakutskaya SDPP-2 on-site racks
Оригинал статьи: Yakutskaya SDPP-2: Heat and Light of the Severe North
Construction of Yakutskaya SDPP-2 is an event for the region more than just of a large-scale. Especially taking into account that the energy situation in Yakutsk and the central part of the republic has developed in a very diffi cult way today. Residents of the capital of the republic know fi rsthand how it is to be left without heat and light when the temperature outside the window is 50 degrees below zero.