The MAIN JOURNAL for POWER GRID SPECIALISTS in RUSSIA
18
NIZHNE-BUREYSKAYA HPP
CONSTRUCTION
The Nizhne-Bureyskaya HPP
project was a part of Byreya Hydro-
power Complex project. Research
on the hydropower potential of the
Bureya River was commenced as
early as 1932 when “Hydroproject”
institute carried out reconnaissance
surveys of the river (an interesting
fact is that following the start
of plant construction works an
exploratory adit of the 1930s was
found at the HPP site). In 1959
a Bureya HPP cascade scheme
was developed, which for the
fi
rst
time ever included the Nizhne-
Bureyskaya HPP (identi
fi
ed as
the “Doldykanskaya HPP” in the
scheme). The site for the Nizhne-
Bureyskaya HPP was chosen in
1978.
The design of the Nizhne-Bu-
rey skaya HPP as a constituent
part of the Byreya Hydropower
Complex was developed by “Len-
hydroproject” institute in 1985, un-
derwent all required examinations
and was approved in 1986. The
plant construction was scheduled
for the fall-off in Bureyskaya HPP
construction works. Project briefs
for Bureyskaya and Nizhne-Bu-
reyskaya HPPs were merged into
Filling the pit of Nizhne-Bureyskaya HPP main structures
New Energy
of the Far East
The Nizhne-Bureyskaya HPP is being erected on the Bureya River in the Amur River
region. The plant is located downstream the powerful Byreyskaya HPP and acts as
its counter-regulator, leveling irregular water discharges.
19
one in 1995 and again separated
in 2003. Plant construction was not
commenced in that period, only
some measures were undertaken
to relocate population from the
fl
ood zone (Bureyskaya HPP
downstream pool and Nizhne-
Bureyskaya HPP reservoir bed).
2007 marked the beginning of
project re
fi
nement works resulting
in signi
fi
cant design changes.
•
Three 107 MW hydro units were
substituted with four 80 MW
hydro units.
•
The right-bank earth dam was
substituted with a concrete
dam.
•
The spillway dam with bottom
outlets was substituted with an
over
fl
ow spillway.
•
A “slurry wall” was introduced
into the channel earth dam
core.
•
Changes were made in the
power distribution scheme: 110
and 220 kV switchyards were
substituted with 220 kV gas
insulated switchgear.
Commencing plant construction
works became possible following
the completion of capital works on
Bureyskaya HPP erection, which
started operating at full capacity
(2010 MW) in 2009 and became
the largest power plant in the Far
East of Russia.
On August 27, 2010, in pre-
sence of V.V. Putin, the start of
construction of the Nizhne-Burey-
skaya HPP, the largest hydropower
plant to be built in present-day
Russia, was announced.
Plant Design
The Nizhne-Bureyskaya HPP
rated capacity is 320 MW,
the ave
rage annual output is
1.65 bln kW•h. Most HPP water-
retaining structures (with the total
length of 745.5 m) will be built
using a channel earth dam with
an impervious element of “slurry
wall” type 400 m long and 42 m
high (max.). Dam foundation will
be made waterproof by building
a puddle clay “slurry wall” that will
cross alluvial deposits up to the
bedrock and a bedrock double-
Bureya River damming
row grout curtain. The earth dam
and the spillway dam will be joined
by means of a concrete transition
abutment.
The spillway dam is made
of concrete and designed for
discharge of water
fl
ows exceeding
the capacity of plant turbines. The
dam length is 123 m, full height is
47.75 m. It is equipped with
fi
ve
over
fl
ow spillways with radial gates
operated by hydraulic drives. Also,
repair gates lifted and lowered by
a gantry crane are to be installed.
Max. dam capacity is 13.332 m
3
/s.
Flow energy dissipation will take
place in a concrete stilling basin
88 m long with baf
fl
e and end walls.
The HPP channel building
96.5 m long and 57.7 m high (max.)
will be located at the right bank. It
will be connected with the spillway
dam by means of a divider wall 73 m
long and with the bank by means of
a bulkhead wall 100 m long (from
there up to the Doldykan River
outlet the bank will be protected
with rubblework). The HPP building
will accommodate four 80 MW
hydro units with Kaplan turbines
PL30-VB-630 operating at the
rated head of 26.1 m and vertical
synchronous hydro generators.
The agreement for supply
of four 80 MW hydro units for
the Nizhne-Bureyskaya HPP
was signed between “Nizhne-
Bureyskaya HPP” (a subsidiary
of PJSC “RusHydro”) and “Power
Machines” in September of 2013.
In accordance with the agree-
ment terms, the liabilities of “Power
Machines” include design, manu-
facturing, supply, installation
supe rvision and installation of four
equipment sets of hydro units,
each of which includes a Kaplan
turbine incorporating an automatic
control system, a hydro generator
with an excitation system, as well
as hydro unit auxiliary equipment.
Special design features of the
equipment include ecologically
safe design of hydro turbines: the
impeller cavity that contains the
blade turning mechanism is not
fi
lled with oil, which eliminates the
risk of oil leakage into water.
Two traveling cranes with
lifting capacity of 250 t each were
installed in the machine hall for
mounting/dismounting of hydro
units. The HPP building will be
equipped with trash racks, repair
and emergency-repair gates,
two gantry cranes (upstream and
downstream). The HPP building
capacity at the rated head is
1.380 m
3
/s (4×345 m
3
/s). Four
power transformers to feed power
to the gas insulated switchgear
are to be installed downstream, at
the machine hall wall.
A non-over
fl
ow concrete dam
76 m long and 19.75 m high (max.)
which closes the waterfront on
20
Start of concrete works
the right bank, a mounting site
and a plant site adjoin the HPP
building. The plant site accom-
modates an engineering and
manufacturing facility and 220 V
switchgear. Electric power is to
be transmitted over OHL 220 kV
through the “Arkhara” (2 OHL) and
“Raychikhinsk” substations.
Nizhne-
Bureyskaya HPP
Construction
in Progress
2011 marked the beginning of
preparatory works that included
construction of a car road 4.1 km
long leading to the plant site and an
overhead transmission line 6 kV,
transshipment base expansion
for construction infrastructure
deployment, and site preparation
for residential developments. The
construction of the foundation
pit of HPP basic structures was
started with low-water cofferdams
in 2011. Three car roads were
built, a concrete batching and
mixing plant was erected, con-
struction of the administration
and management building and
builders’ lodgings was in pro-
gress. In 2012 the preparatory
works were mainly completed: the
foundation pit cofferdams were
built up to design dimensions,
construction of a “slurry” wall for
the cofferdams was commenced.
The construction of the
administration and management
building, concrete facility with a
construction technology laboratory,
construction mechanization
and main equipment facilities,
220/35/6 kV “Stvor” substation,
builders’ lodgings was completed.
JSC “Trest Gidromontazh”
became the prime contractor for
the construction works.
The foundation pit for basic
structures was dried up (con-
struction of the “slurry” wall in the
cofferdams was completed at the
beginning of March 2013) and
concrete works at the spillway dam
and right-bank non-over
fl
ow dam
were started in 2013. JSC “Power
Machines” was engaged as the
supplier of hydropower equipment
(turbines and generators). In 2014
concrete pouring for the HPP
building was commenced.
By the end of 2015, about 90%
of concrete had been already
poured, hydro turbine inserts
had been installed, channel earth
dam construction and hydro-
mechanical equipment mounting
works had been started.
On April 19, 2016 the Bureya
River at the Nizhne-Bureyskaya
HPP site was dammed. The
previous large-river damming
in Russia took place in 2011
during construction of the
Ust-Srednekanskaya HPP in
Magadan Region. Preparation for
the damming was started in March
2016, when the foundation pit of
main concrete plant structures
was
fi
lled. Commissioning of the
fi
rst hydro units of the Nizhne-
Bureyskaya HPP is scheduled for
the end of 2016.
Social and
Economic
Effects
of Nizhne-
Bureyskaya HPP
Construction
Implementation of the Nizhne-
Bureyskaya HPP construction
project has positive social and
economic effects for the Far East
and Russia, as a whole, including:
•
reduction of current generation
costs in the UPS of the East,
complemented by eliminating
restrictions of the Bureyskaya
HPP and thermal generation
substitution;
•
possibility of transfer of nearby
settlements from heating by
expensive oil- and coal-
fi
red
boiler-houses to heating by
electric boiler-houses, with
reduction of consumer charges
for heat;
•
creation of vacant positions for
buil ders who completed their
work at the Bureyskaya HPP
(2 000 people) and reduction
of population migration from
the Far East;
•
engaging Russian manu
fac-
turers and contractors;
•
growth of tax revenues in
budgets of all levels;
•
growth of the population pur-
chasing power in the Amur
River region.
Electric power of the plant will
be directed to the energy system of
the Far East to supply both existing
and prospective consumers, such
as Vostochny Cosmodrome, trans-
port infrastructure facilities (in par-
21
Earth dam erection
ticular, the “Power of Siberia” gas
pipeline), mining enterprises.
In addition to electric power
production, the Nizhne-Burey-
skaya HPP is designed to opti-
mize operation of the high-
capacity Bureyskaya HPP. One
of the important functions of the
Bureyskaya HPP is operation in
the irregular part of the load curve.
For example, in the morning,
when demand for power in the
energy system rises sharply,
the plant operates at a higher
capacity and the amount of water
discharged via hydro units sharply
increases. At the same time, at
night, when demand for power in
the energy system decreases, the
plant load and, correspondingly,
water discharges are signi
fi
cantly
lower.
Variations in the amount of
discharged water cause signi-
fi
cant river level
fl
uctuations. Pre-
venting them is the purpose of
construction of a counter-regulator
HPP with a relatively small water
reservoir, where discharge ir regu-
larities are balanced. The Nizhne-
Bureyskaya HPP will be the third
counter-regulating HPP in Russia
(the
fi
rst and the second ones are
the Miatlinskaya and Maynskaya
HPPs that balance discharges of
the Chirkeyskaya and Sa
yano-
Shushenskaya HPPs, respec-
tively).
Also, the Nizhne-Bureyskaya
HPP will have certain
fl
ood protec-
tion effect by smoothening Byreya
water reservoir discharge peaks.
With regard for the lessons of the
heavy
fl
ood of 2013, the decision
was made to improve the
fl
ood
protection capabilities of the plant
by introducing changes into its
design that enable increasing
the available storage capacity of
the reservoir. The Nizhne-Burey-
skaya HPP reservoir will play an
important role in prevention of
winter under
fl
ooding of settle-
ments, which will make it possible
to use regulation potential of the
Bureyskaya HPP without any
restrictions.
Resettlement of the population
from the Nizhne-Bureyskaya
HPP reservoir
fl
ood zone took
place during Bureyskaya HPP
construction. PJSC “RusHydro”
allocated money for
fl
ood zone
sanitation, deforestation and ar-
cheo logical surveys.
In Harmony
with Nature
The Nizhne-Bureyskaya HPP
project meets the highest eco-
logical standards. At the support of
“RusHydro”, a set of compensation
measures is undertaken that
includes creation of “Bureysky”
natural park, improvement of the
living environment for animals and
birds, transfer of rare plants from
the
fl
ood zone.
The project of compensation
measures is implemented within
the framework of the quadruple
cooperation agreement between
the Ministry of Natural Resources
of the Amur River region, the
Agency for Protection, Monitoring
and Regulation of Use of Fauna
and Habitats of the Amur River
region, JSC “Nizhne-Bureyskaya
HPP” and United Nations De-
velop ment Program Project. The
latter includes the project “Main-
streaming biodiversity con
ser-
vation into Russia’s energy sector
policies and operations” of the
United Nations Development
Program, Global Environment
Facility (GEF) and the Ministry of
Natural Resources and Ecology
of the Russian Federation. The
agreement provides for a set of
measures on reducing Nizhne-
Bureyskaya HPP construction
effects for the environment,
the most important of which is
creation of “Bureysky” Natural
Park.
A natural park was created
in the Nizhne-Bureyskaya
HPP impact area with the
support of hydropower
engineers
22
Manufacturing of equipment
for the Nizhne-Bureyskaya HPP
“Bureysky” Natural Park is lo-
cated in the territory of Bureysky
and Arkharinsky districts of the
Amur River region, in the impact
area of the Bureya Hydropower
Complex that includes the
operating Bureyskaya HPP and
Nizhne-Bureyskaya HPP under
construction. The park spans the
territories of existing “Zhe
lun-
din sky” and “Urochishche Irkun”
reserves, as well as additional
areas upstream and downstream
the Nizhne-Bureyskaya HPP re-
ser voir. The total area of the
park is 132 thousand hectares.
Compensation measures direc-
ted at creation of favorable con-
ditions for
fl
ora and fauna in the
reservoir area and downstream
are undertaken in the park. In par-
ticular, they include con
struc tion
of a network of feeding stations for
hoofed animals and placement of
nest boxes for the rare Mandarin
Duck.
Innovative
Technologies
Nizhne-Bureyskaya HPP
construction employed a number
of innovative solutions directed
at reduction of construction terms
and costs as well as quality
improvement. For example, an
earth dam with a conventional
impervious element represented
by a clay loam core (provided
for by the plant design initially)
was replaced with a “slurry wall”
of clay-cement-concrete piles.
Such a design of a large-scale
dam impervious element is used
in Russia for the
fi
rst time and is
one-of-a-kind in the world.
Another innovative solution
is the numerical hydrodynamic
model of the “Bureyskaya HPP –
Nizhne-Bureyskaya HPP – Nizh-
ne-Bureyskaya HPP down stream
pool” system.
The model will give information
support for decision-making
concerning river
fl
ood discharges
with account for storage capacity
of the Bureyskaya HPP – Nizhne-
Bureyskaya HPP cascade re-
ser voirs. It enables automation
of calculations, integration and
visualization (in a three-dimen-
sional model) of reservoir ope-
rating conditions in a single hard-
ware and software system, in
a shared coordinate system.
The model was developed
with the use of modern high-
accuracy survey methods: laser
aero scanning, bottom survey
by echo sounding, photo
fi
xation
with coordinate referencing for
engineering structures located
in the
fl
ood zone of the Nizhne-
Bureyskaya HPP reservoir.
The geographic information
system (GIS) “NBHPP reservoir
territory” was deployed. A three-di-
mensional digital map for the pro-
ject was developed (Scale 1:2000).
Besides, a shared environment for
real-time joint work on the project
during of
fi
ce and laboratory studies
was created. This made it possible
to arrange parallel work of a large
number of contractors in shared
information space with all project
participants’ access to any relevant
information.
To simulate
fl
ood-control
storage of the reservoir during
water discharges, to calculate
reservoir volumes and depths,
a summary network terrain model
was developed. Environment for
interactive visualization of objects
simulated in CAD-systems was
created.
The works on model develop-
ment have signi
fi
cant economic
impact: the acquired high-ac-
cura cy, detailed data were used
in development of working docu-
mentation for the Nizhne-Burey-
skaya HPP reservoir, which greatly
accelerated customer docu menta-
tion furnishing process.
Proven methods signi
fi
cantly
reduce the time of surveys for
development of any design or
working documentation, especial-
ly for large-area and linear faci-
lities, including those intended for
building hydraulic structures, water
reservoirs, roads, transmission
lines, etc.
The reservoir simulation infor-
mation model is a part of shared
information environment for
design process and project data
control (HydroPRO system). This
system is used in construction of
hydropower plants in Russia for
the
fi
rst time. Now, thanks to this
HydroPRO system and Nizhne-
Bureyskaya HPP operation ex-
perience, it has become possible
to design new plants, carry out
project examinations and super-
vise construction works in less
time and more easily.
Оригинал статьи: Nizhne-Bureyskaya HPP Construction
The Nizhne-Bureyskaya HPP is being erected on the Bureya River in the Amur River region. The plant is located downstream the powerful Byreyskaya HPP and acts as its counter-regulator, leveling irregular water discharges.