The MAIN JOURNAL for POWER GRID SPECIALISTS in RUSSIA
52
NEW PROSPECTS OF THE
FAR EAST POWER INDUSTRY
The Russian Far East is much
reliant on TASED foundation. It is
supposed that the organization
of these platforms will allow to
realize large-scale projects on
pro
fi
table terms at the expense
of the particular tax regime and
other preferences, and as for Far
Easterners, it will help to improve
living circumstances due to the
development of infrastructure and
new vacant positions.
The corresponding infrastruc-
ture shall be developed according
to the requirements of the advanc-
ing social and economic develop-
ment territories. At this stage of
the law implementation in all ter-
ritories there is the preparation
for construction of thoroughfares,
erection of TASED objects and
engineering infrastructure. But
the power engineering is still the
basis point for implementation of
almost all projects. It is important
to organize the electrical network
infra structure in TASED creation
areas, the other production sphe-
res will make their way after power
engineering.
Ambitious targets for connection
of TASED installations to power
supply are assigned to Far East
power engineering specialists.
Р
ower supply
In the spring of 2015 the Federal law “About the Territories of the Advancing
Social and Economic Development in the Russian Federation” came into force.
The law became a starting point for economy of the Far East encouragement and
various state programs running.
53
Specialists of the companies have
already started the preparation of
energy infrastructure units in six
regions of the Far East. As a result
of the adopted laws on TASED
this work became possible in the
Amur River and Sakhalin regions,
Primorsk, Khabarovsk and Kam-
chatka regions, the Republic of
Sakha. All units have to be con-
nected to power supply during
2016-2018.
Besides, DRSK (part of PJSC
“RAO Energy Systems of the
East”) power engineering specia-
lists are preparing for large-scale
construction of electric substation
and the HVTL for the connection
to power supply of units of the gas
and transportation system “Force
of Siberia” and the Amurskaya gas
processing plant.
Today the companies of the
Holding “RAO ES of the East”
order projects of future power
facilities, the equipment, lay
tracks of the new high voltage
lines on maps, look for contractors
for the construction – generally,
they are actively busy by the
implementation of requests for
technological accession of TASED
future units, “Power of Siberia”
gas transmission system and
Amurskaya gas-processing plant.
“One of the key problems of
the Far East power engineering
is a small amount of large con su-
mers”, Sergey Tolstoguzov, PJSC
“RAO Energy Systems of the
East” CEO, tells. Also he notes
that today the situation is a little
changed. Construction of new
power facilities is an indicator of
industrial and economic growth of
the region. The huge work has to
be done in the future. It is required
to contribute more
fi
nancial and
human resources. But gradually,
step by step, we will complete the
task that the government has set
for us”.
Estimating the scales of units
construction within TASED power
engineering specialists clearly
understand the discrepancy of
capacity of the existing electrical
network infrastructure to qualify-
ing standards. According to the
available requests to DRSK for
the connection of units in TASED
until the end of 2018 DRSK needs
to provide the load till 210 MW for
customers with the subsequent
load gain till 250 MW. Kamchatks-
Energo needs to provide a load
gain of 43 MW, YakutskEnergo –
4 MW.
“The company has already
started the preparation of new
power facilities for TASED
development in three regions
of the Far East. It is important
to emphasize that the power
engineering is a basis point of
construction not only in TASED,
but also all infrastructure for that.
We are short in time. Therefore
today the support and coordination
of actions of authorities and
investors are very important”, Yury
Andreenko, CEO of JSC DRSK
emphasized.
Т
ASED
Among the largest applicants
on ful
fi
llment of technological
connection to the electrical
networks in the Amur River region
is TASED “Priamurskaya” oriented
to import-substituting production
of construction materials and oil
products, and also to rendering
the transport and logistic and other
services. Within the creation of
this territory there is planned to
construct the Amurskaya petroleum
processing plant near the village
DRSK power engineering specialists have started new
power facilities preparation for the development of TASED
in three regions of the Far East
54
Beryozovka of the Ivanovskiy
Region. The contracted capacity of
the connected unit will be 50 MW.
Power engineering specialists
have to build the high voltage line
of 110 kV about 35 kilometers long
and a new electrical substation of
110 kV.
For power supply of oil-extract-
ing and formula-feed plants of
agro-industrial Amurskaya TASED
“Belogorsk” total load of 7 MW
there will be necessary to recon-
struct the electrical substation of
35/10 kV and to build the high volt-
age line of 10 kV with the electrical
substation of 10/0.4 kV.
There is planned to con-
nect such large units as TASED
“Mikhaylovsky” and “Bolshoy Ka-
men” (A Big Stone) to the DRSK
network in Primorsky region.
TASED “Mikhaylovsky” speci-
alizes in location of agro-industry
and the centers of processing and
logistics of agricultural products
in Chernigovsky, Spassky and
Mikhaylovsky municipal districts of
Primorsky region. The maximum
capacity will be 56.65 MW. For
TASED “Bolshoy Kamen” where
a ship-building cluster is based on
the Far East center of shipbuild-
ing and ship repairing, the capac-
ity of the connected units will be
about 31.7 MW. PDA in Primorsky
region will allow to enhance the
effect of shipbuilding development
based on the complex “Zvezda”.
The work on ensuring power
supply of air terminal complex of
the Khabarovsk International Air-
port in Khabarovsk region is car-
ried out for development of TASED
“Khabarovsk”. Within the next four
years the airport of the regional
capital will become one of the
largest air hubs of the interna-
tional importance in the Far East.
The additional electric capacities
will be necessary for it. For this
purpose the events for overall re-
construction of the electrical sub-
station of 110/35/6 kV “GVR” sup-
plying with electricity the airport
are carrying out. Today there was
completed the installation of the
third power transformer of 110 kV
that will allow to increase the elec-
tric capacity of the electrical sub-
station by 25 MBA (or 50 percent)
of the existing indicators. Power
supplying possibilities of the reno-
vate center will meet not only cri-
teria of the extending air transpor-
tation center, but also it will allow
to connect new applicants to the
DRSK network. DRSK experts
plan to complete the reconstruc-
tion of the electrical substation
110/35/6 “GVR” by the end of this
year.
Within TASED “Khabarovsk”
there is performed the preparatory
work on connection of the objects
for the platform “Rakitnoe”, in par-
ticular, the plant on recycling of
scrap steel of nonferrous metals,
the contracted capacity is 55 MW.
The documents for technological
connection of the industrial park
“Avangard” objects in Khabarovsk
(capacity is 14.6 MW) are pre-
pared. It will be necessary to con-
struct the electrical substation of
110 kV with the high voltage line
of 110 kV for power supply.
The issues concerning the pow-
er supply of objects of the platform
“Parus” in TASED “Komsomolsk”
in Komsomolsk-on-Amur (capacity
is 9 MW) are discussed.
Within the engineering infra-
structure development for the
territory of the advancing de-
velopment “Kamchatka” PJSC
“KamchatksEnergo” will provide
the energy to the future platform
of a tourist cluster in borders of
the Paratunsky rural village, the
maximum capacity is 7.1 MW. The
Kamchatka power engineering
Substation 110/35/10 kV «GVR» is the main supplying
center of the Khabarovsk airport. Specialists plan
to
fi
nish reconstruction by the end of the current year
55
spe cialists plan to construct a new
electrical substation of 35/10 kV
“Tourist cluster” (2×10 MBA),
to perform seven complete and
transforming substations of
10/0.4 kV, to install about 14 km of
new power lines in 2016-2017 in
the village Paratunka. Besides, in
2016-2017 within the investment
program of the company for con-
nection of new objects there will
be performed the reconstruction
of own objects – air-lines of 35 kV
“Bugry – Paratunka” and “Sos-
novka – RPC”.
PJSC “YakutskEnergo” per-
forms the work concerning the
construction of the power supply
complex of the industrial park in
the village Kangalassy, capacity
is 2.955 MW. The input is planned
in 2018. The project provides to
enter the production of expanded
polystyrene, sustained
fi
re boilers,
polyethylene pipes, insulating
glass units, the plastic container,
production of biological petroleum
sorbents and chemical production
near the capital of Yakutia.
In 2020 in the Megino-Kanga-
lassky ulus of the Republic of Sa-
kha (Yakutia) there is planned the
input of the territory of the advanc-
ing development “Za rechie”. It will
include two plants: production of
methanol and the condensed na-
tural gas. “Yakutsk Energo” will pro -
vide technological connection of
these objects with capacity of 56 MW.
Power Facilities
for Gas Workers
“Gazprom”, the large industrial
power consumer comes into the
Amur River region. Taking into ac-
count the ful
fi
lment of all requests
for technological connection that
the company gets today from gas
workers the load in the DRSK net-
works will grow almost by 10%.
In the Amur and southern Yakut
DRSK branches there are already
25 requests for technological con-
nection of objects of cross-country
gas pipeline “Force of Siberia” and
11 requests concerning the ob-
jects of the Amurskaya GPP. The
total contracted capacity is about
75 MW. 56 MW of them are in the
Amur River region.
“The representatives of authori-
ties are involved in the organiza-
tion of power supply of the objects
where it is necessary to provide
the main work on connection of
linear-type facilities and the Amur
GPP. Together with the Amur re-
gion government we managed
to reach the agreement on all is-
sues requiring joint consideration
in short terms,” – Yury Andreenko
emphasizes.
The electrical substation “Za-
vodskaya” of 35/10 kV is erecting
for providing technological con-
nection to electric networks of two
objects of LLC “Gazprom Pro-
cessing Blagoveshchensk”. One
of them is a platform of manufac-
tured buildings and constructions
of the construction camp as a part
of the “The Amurskaya GPP”
building. The second is a building
area and auxiliary objects of that
plant. According to two requests
the general contracted capacity is
9.8 MW.
Today three objects of the gas
pipeline are already connected
to the electric network ahead of
schedule. Now specialists calcu-
late the amount of construction
of power lines and the electrical
substations and also investments.
All requests for the connection of
objects need to be ful
fi
lled until the
end of 2017.
New power units construction
is one more proof of economic
development of the region
Оригинал статьи: New Prospects of the Far East Power Industry
In the spring of 2015 the Federal law “About the Territories of the Advancing Social and Economic Development in the Russian Federation” came into force. The law became a starting point for economy of the Far East encouragement and various state programs running.