The MAIN JOURNAL for POWER GRID SPECIALISTS in RUSSIA
3 - 6 J U N E 2 0 1 9
MADRID, SPAIN
The MAIN JOURNAL for POWER GRID SPECIALISTS in RUSSIA
3 - 6 J U N E 2 0 1 9
MADRID, SPAIN
1
4
d
ig
it
a
l
t
r
a
n
s
f
o
r
m
a
t
io
n
digital transformation
Digitalization of Northern
Power Distribution Zone
in PJSC "LENENERGO"
Igor KUZMIN,
fi rst deputy director
general — chief engineer
of PJSC "LENENERGO"
Niyaz MAGDEEV,
deputy chief engineer on
technological development
and innovation of PJSC
"LENENERGO"
Yuriy GULIM,
main specialist of Depart-
ment of technological
development and
innovation of PJSC
"LENENERGO"
Digital transformation of electric power industry is one of the
purposes of the national program “Digital Economy of the Russian
Federation” (approved by the Russian Federation Governmental
Order no. 1632-
р
dated 28.07.2017 and recognized by the Russian
Federation Presidential Decree no. 204 dated 07.05.2018). "Digital
Transformation 2030"
с
oncept was developed by PJSC "Rosseti"
for establishing one-for-all approach to the digital transformation
of processes in power grid. In accordance with the principal provi-
sions of the Concept, digital transformation of PJSC "LENENERGO"
electrical grid is performed and a pilot project to create digital
power distribution zone is implemented.
T
he digital network assumes a breakthrough
state of power system characterized by integra-
tion of electrical network, load customers and
power generators into a single automated sys-
tem at a technology level.
First of all, the network digitalization is expected the
following:
• resilience after power outages;
• network resilience to physical and cybernetic interfer-
ence of intruders;
• ensuring required power quality;
• ensuring the synchronous operation of generation re-
sources and energy storage system;
• potential active involvement of consumers in network
operation;
• integration of new high-tech products into network.
As a part of an interdisciplinary approach to digital
transformation of networks, the project strategy (Fig-
ure 1) includes the implementation of measures in the
following areas:
• creation of a Single Grid Control Center (GCC) and
the introduction of automated dispatch management
system for network operation control with an advanced
complex of computational analysis;
• construction of 35-110 kV digital substations;
• modernization of secondary infrastructure in operat-
ing 35-110 kV substations;
• automation of 6-20 kV network (creation of digital
power distribution zones);
• introduction of electrical energy smart metering to
reduce business losses and to use accounting records
in computational and analytical functions;
• creation of multiservice communication network.
As a result of the interdisciplinary approach to net-
works modernization and subsequent parallel operation
of all functional areas, technical and economic eff ects
from the implementation of PJSC "LENENERGO" digital
transformation concept could be achieved.
1
5
Under the multiple application of modern technolo-
gies aimed at digitalization, it is planned to achieve the
following eff ects:
• reduction of power losses;
• reduction of operating expenses;
• improvement of reliability indexes (average outage
duration and frequency of power failures) by 50%;
• ensuring greater availability of technological connec-
tion for new consumers.
The project will be implemented since 2018 to 2030.
Project implementation will consist of three main stages.
On the fi rst stage preparation of a technological base
for digitalization is planned, as well as introduction of
a modern network management system under creation
of a single grid control center for PJSC "LENENERGO".
A number of pilot multiple-purpose projects for the sub-
sequent distribution of the most effi cient business solu-
tions in PJSC "LENENERGO" will be also implemented.
The stage is scheduled for completion in 2022.
The second stage is aimed at the complete automa-
tion of power grid facilities and management process-
es, monitoring and "bottleneck" searching. This stage
will eliminate the actual problems in the organization of
ope rational and technological management. Also, it will
identify targets for investment over the next 5-10 years.
The stage is scheduled for completion in 2025.
In the third stage the digitization of the main elements
of digital network (35-110 kV substations and power dis-
tribution zones) will be completed. In addition, during this
stage introduction of technologies based on artifi cial in-
telligence and machine learning will be developed. Then
Big Data technology comes into play when all available
methods of automation and control are implemented
and the effi ciency increase task is already not so impor-
tant. It analyzes a huge amount of data, searches for
Fig. 1. Structure of the digital transformation of PJSC "LENENERGO" electrical grid
Single Grid Control Center
(GCC)
110 kV network
35 kV network
Сonsumers
0.4-20 kV network
MANAGEMENT COMMITTEE
ON IMPLEMENTATION OF PROJECTS AIMED
AT DIGITAL NETWORKS CREATION
Head of the Management Committee:
director general of PJSC "LENENERGO"
WORKING GROUP ON IMPLEMENTATION OF
PROJECTS AIMED AT DIGITAL NETWORKS
CREATION
Head of the working group:
fi rst deputy director general - chief engineer
“Single Grid
Control Center”
direction
“Digital
substations”
direction
“Digital power
distribution zone”
direction
Research institutes, leading equipment manufacturers,
software developers, design organizations
Fig. 2. Project group
new dependences of key performance indicators of the
company and suggests creation of new company man-
agement algorithms. This process is aimed at a qualita-
tive leap in improving effi ciency of all processes and it
will provide at least 10% growth of the main parameters:
reliability, effi ciency, workforce productivity. The stage is
scheduled for completion in 2030.
A number of working groups on digitalization areas
chaired by the Management Committee (Figure 2) was
The 25th CIRED Session
Special issue, June 2019
1
6
D
I
G
I
TAL
TRA
N
SFORMAT
I
O
N
created for the adoption of collegial technical decisions
in PJSC "LENENERGO" and for implementation of
projects aimed at digital networks establishment.
The fi rst deputy director general – chief engineer
of PJSC "LENENERGO" is responsible for the imple-
mentation of pilot projects aimed at digitalization. The
working group participants: the unit of technological de-
velopment and innovation, the unit of information tech-
nology, the unit of service implementation and devel-
opment, the unit of prospective development, the unit
of operative and process management and situational
management, the economic unit, the unit of fi xed assets
construction, security and representatives of operating
branches. The working group consists of 42 people in
total.
This organization structure allows the working group
to interact qualitatively with research institutes, equip-
ment manufacturers, design organizations and to de-
velop the most eff ective generic solutions for later use
in digitalization of PJSC "LENENERGO" network.
An important step of the transition to digital networks
is the creation of Single Grid Control Center and intro-
duction of operative controlling complex with advanced
computational and analytical functions for managing
digital electrical network.
On the sidelines of the Single Grid Control Center
creation, work on pilot projects aimed at creating digital
networks (digital power distribution zone, digital sub-
stations, active-adaptive network sections in various
power distribution zones) will be performed. According
to the results of the pilot project implementation, the
most eff ective business solutions will be implemented
throughout the network of PJSC "LENENERGO".
Digital power distribution zone is a highly automated
power distribution area controlled in real time. It pro-
vides observability and controllability
through digital communication networks.
Also, it monitors the operating conditions
and modes of power system equipment.
Digital power distribution zone has self-
test functionality and self-repairing func-
tions, as well as smart metering of elec-
tric power consumption.
The pilot project aimed at digitiza-
tion of 6-10 kV distribution electrical
networks is being implemented in PJSC
"LENENERGO" as a part of Northern
power distribution zone served by PJSC
"LENENERGO" branch — "Cable Net-
work" (Figure 3).
So far, the Northern power distribu-
tion zone operates 0.4-10 kV electrical
network in the Kalininskiy and Vyborgs-
kiy administrative regions of St. Peters-
burg. In the customer basin of power
distribution zone (the area is 50.11 km
2
)
1048 transformer substations and
6-10 kV power distribution stations are
located, length of 6-10 kV cable lines is
2089.84 km, length of 0.4 kV cable lines
is 1032.17 km. About 850 000 people live
in the area of Northern power distribution
zone responsibility. Watt consumption is ~380 MW, and
the secondary power need is ~101 MW. Electric power
losses are 13.58%.
The project of creating a digital power distribution
zone is planned to be divided in stages in 2018-2021.
As a part of the
fi rst stage
, introduction of digital
network elements in the Northern power distribution
zone will be provided: short-circuit current indicators,
data aquisition and data communication units, fi bre-
optic communication lines, automated information and
measurement systems of electricity revenue metering,
controllers. Mentioned elements will ensure the net-
work observability.
The following stages of creating a digital power dis-
tribution zone become possible only after performing
an inclusive design. Termination of design and survey
work is scheduled in 2019.
As part of the
second stage
, implementation of
a digital power distribution zone management system
(including the functions of automatic fault isolation, net-
work self-repairing) is planned. The management sys-
tem will be based on the operative dispatching service
of the Single Grid Control Center (within the framework
of the GCC project). The dispatching service will com-
bine advanced computational and analytical functions
and integration of systems for automated information
and measurement, electricity revenue metering, short-
circuit current indication, operating telecontrol and
communication with power distribution zone facilities.
The stage completion is scheduled in 2020.
As part of the
third stage
, installation of managed
network elements and the later remote control of 100%
power distribution zone facilities is planned. Subse-
quent subsystems integration into the implemented
software and hardware complex of the digital power
Mostly
residential
electrical
customers
Petrodvortsovy
Pushkinsky
Kolpinsky
Kurortny
Vybogsky
Primorsky
Petrogradsky
Tsetralnyy
Vasileostovsky
Admiralteisky
Kalininsky
Krasnogvardeysky
Nevsky
Frunzensky
Kirovsky
Krasnoselsky
Moscovsky
Krondshtat
~380
MVA
Fig. 3. Northern power distribution zone served by PJSC "LENENERGO"
branch — "Cable network"
1
7
distribution zone management system will be also per-
formed. Implementation of self-repairing functions and
automatic optimization of network operation is planned.
The stage completion is scheduled in December 2021.
As a result of the project implementation, elec-
tric power losses reduction by 7.45% is expected. The
achievement of such a result will be facilitated by install-
ing systems of automated power consumption metering,
automatic monitoring of electricity imbalance, unac-
counted and non-contractual consumption, automatic
monitoring of areas with non-standard power quality.
The digital power distribution zone project will have
a signifi cant impact on the fi nancial indexation. Engi-
neering process automation will result in optimization
of the organization structure of power distribution zone.
The maintenance costs will be reduced by 10.8% (us-
ing low-maintenance equipment, simplifying calibration
of instruments, remote diagnostics and self-diagnostics
of equipment and systems). Cost of fuel and lubricants
will be decreased by 50%. As a whole, this will result in
cutting the specifi c operational expenditures (OPEX) of
power distribution zone at least by 15.2%.
Approximately the same level (15%) is expected to
be achieved while cutting capital expenses (CAPEX).
The eff ect is planned to be achieved by reduction in
requirements for new construction (or facilities reno-
vation and transformer capacity increase) through en-
suring the network observability and estimating power
fl ows in various modes based on actual data and au-
tomatic mode optimization (balanced load is ensured).
An added value will be achieved due to the potential
automatic design engineering (in CAD system) cutting
of the design and survey work cost. In addition, due to
digital technology, the volume and cost of commission-
ing work are reduced. Technological diversity of stan-
dard facilities and digital networks should be taken into
account: when using digital technology, it is assumed
a massive reduction of copper connections.
Electrical network digitalization will signifi cantly im-
prove power supply reliability. Based on the analysis of
the completed stages of design and survey work con-
cerning creation of active adaptive networks, the intend-
ed reduction of SAIDI and SAIFI indicators by the end
of the pilot project to create a digital power distribution
zone was determined as 50% in relation to the current
status. It is confi rmed by expert assessment of operating
electrical networks. SAIDI and SAIFI decline will occur
as the introduction of equipment aimed at network digi-
talization. The eff ect will be achieved through the net-
work self-restoration function, automated localization of
failed elements, balance load, monitoring, self-diagnos-
tics and remote controllability of the network.
According to the results of the project implementa-
tion, internal business processes of PJSC "LENENER-
GO" will be optimized (Table 1).
Electrical network digitalization will infl uence not
only on the effi ciency of power grid operation, but it will
also have a signifi cant impact on the service quality for
an ultimate customer:
• the time for technological connection of consumers
will be reduced by introducing a settlement function
for modeling requirements specifi cations and dead-
lines to fulfi l the engagements on technological con-
nection, as well as decreasing of new construction
for technological connection due to balanced load;
• power quality will be improved (voltage and fre-
quency deviation) due to the optimization of electri-
cal network modes and schemes as well as power
quality monitoring;
• power supply interruption time will be shortened
due to the network controllability, the introduction
of a self-restoration function and automatic localiza-
tion of failed elements.
PJSC "LENENERGO" leaders and experts believe
as well that electrical grid digitalization will help not
only to achieve economic and technical eff ects when
solving application tasks, but it will signifi cantly infl u-
ence the following global factors of economic develop-
ment and life quality improvement:
1) high level of environmental conditions, high stan-
dards of electric power supply and service quality;
2) competitive advantage of domestic power engineer-
ing industry and information systems;
3) environmental improvement through reducing loss-
es and applying new energy-saving technologies,
as well as using eco-friendlier equipment.
Table 1. Planned changes of business processes in PJSC "LENENERGO" as a result of the project implementation
Indicator
Defi nition
Adjustment of
engineering processes
Automation of electrical mode control, automated localization of failed elements, automating
response to changes in the electrical grid, followed by the ultimate solutions to prevent
accidents and to ensure power supply with increased reliability and economic effi ciency.
Adjustment of
business processes
Automation of emergency reserve, automated suggestions for maintenance and
investment programs, modeling of requirements specifi cations and deadlines to implement
technological connection, automatic interaction with consumers.
Changes in the organiza-
tion structure of power
distribution zone
In accordance with the target structure of the Single Grid Control Center, dispatching
department is excluded from the power distribution zone. Further changes in the
organization structure are possible.
Adjustment of standard
number of employees
Through the automation of process management (control of switching devices, automatic
localization of the failed elements, etc.), as well as business processes, it is expected the
optimization of standard number of employees.
The 25th CIRED Session
Special issue, June 2019
Оригинал статьи: Digitalization of Northern Power Distribution Zone in PJSC “LENENERGO”
Digital transformation of electric power industry is one of the purposes of the national program “Digital Economy of the Russian Federation” (approved by the Russian Federation Governmental Order no. 1632-р dated 28.07.2017 and recognized by the Russian Federation Presidential Decree no. 204 dated 07.05.2018). “Digital Transformation 2030” сoncept was developed by PJSC “Rosseti” for establishing one-for-all approach to the digital transformation of processes in power grid. In accordance with the principal provisions
of the Concept, digital transformation of PJSC “LENENERGO” electrical grid is performed and a pilot project to create digital power distribution zone is implemented.